OFFICIAL BUILDER WEBSITE

PRE-CONSTRUCTION CONDOS IN MIDTOWN TORONTO

Sixty Five Broadway is a luxurious pre-construction condominium development at the heart of midtown Toronto. With distinctive towers soaring above a four-storey podium, a private courtyard off Broadway is your tranquil oasis from the action of Yonge and Eglinton. The landscaping is soothing and minimal with manicured walkways and seasonal plantings. Beauty and serenity are by your side as you arrive home.

Dynamic and connected, with a touch of calm restraint. An intricate filigree of perforated metal screens zigzags up the façade, subtly hiding balconies while letting in natural sunlight. The stepped pattern culminates in a dramatic roof overhang, giving the building a dynamic presence.

Browse Suites

Atop the four-storey podium, the outdoor Rooftop Terrace is an inviting place to enjoy warm summer evenings overlooking our vibrant city. Discreet privacy screens, lush landscaping, lounge style seating, and barbecue pods add to the ambience. Gather your friends and enjoy the fresh air.

Browse Amenities

...

CONSTRUCTION UPDATE

As of May 1, 2024
 

The transformation at Sixty Five Broadway is well underway, and it’s a sight to behold. The once quiet street is now bustling with activity as shoring and excavation have been ongoing since November 2021. Two cranes now tower over the site, providing a glimpse of what’s to come. Site servicing has commenced and you won’t believe the progress that’s being made. The site is taking shape and it’s clear that something magnificent is being built. Follow us on Instagram and YouTube to stay up-to-date and learn more about these and other upcoming projects.

 
  • Zoning Bylaw (Complete)
    Formal Zoning By-law was issued on March 12, 2021.
  • Construction Management Plan (Complete)
    Our Construction Management Plan has been approved by City staff and Community Council approval on June 2021.
  • Notice of Approval Conditions Status (Complete)
    Received its Notice of Approval Conditions (NOAC) on April 21, 2021.
  • Building Permit
    Received Demolition Permit on May 28, 2021 and Shoring & Excavation Permit on May 25, 2021. Received Foundation Permit on October 26, 2022.
  • Site Plan Approval (Complete)
    Received Site Plan Agreement on December 9, 2022.
Construction Status
  • Concrete forming: Complete on all floors
  • Window Installation: Complete up to 30th floor
  • Building Envelope: Complete up to 25th floor
  • Mechanical Rough-in: Complete up to 8th floor
  • Electrical Rough-in: Complete up to 8th floor
  • Drywall: Complete up to 6th floor

SALES CENTRE

BY APPOINTMENT ONLY

3985 Highway 7 East, Suite 202, Markham
(2528 Yonge Street Sales Centre is Now Closed)
Mon-Sun: By appointment only

Office: 416-461-9235  |  Mobile: 647-462-3131
info@sixtyfivebroadway.com